The Department of Infrastructure of the City of Mazarrón is running currently works in the Bay Management in the vicinity of the Sierra de las Mulberry Street between Marsh Street and Sierra Madroñera Bridges.
The improvements are being carried out in full heart of Puerto de Mazarron are the renewal of sanitation and safe water as well as installing new lighting.
For sanitation it is using a corrugated PVC pipe 400 mm, a drinking water pipeline of 150 mm FD and lighting lamps 10 m and 150 w.
The works, whose tender budget is 203,552.02 euros, will be ready within four months.
Source: Ayuntamiento de Mazarrón